Stop Chicken Little: The Truth about Traffic in Portland, Maine |
|
Stevens Avenue Project: Portland DPW CMAQ Application , annotated
If you have looked at
the DPW application for funds and it seemed OK, try this one:
it has the problems denoted in red. I've removed the page numbers and formatting so
as to fill the space.
STEVENS
AVENUE TRAFFIC CALMING PROJECT (CMAQ) APPLICATIONS FEDERAL AID PROJECT NO. CM‑6869(00)/PIN
6869.00 This
booklet contains copies of the CMAQ applications filed by the City of Portland
with the State of Maine, for funding the Stevens‑Avenue Traffic Calming
Project Prepared by The Alliance for
Transportation Choice P.O. Box 10625, Portland ME 04.104 IA 8
71‑9228 July 21, 1997 (Editors note: compiled 10/1999, from booklet found at Burbank library, Portland, Maine.) CITY OF PORTLAND, MAINE
CITY
COUNCIL AGENDA REQUEST FORM
Copies to be submitted
(with supporting material) at least 12 days before Council meeting: Copies to:
Nadeen Daniels. Assistant City
Manager/Director P W
(William Bray signature)
William J. Bray, Dep. Director PW Date
1. Council
Meeting at which action is requested: Date:
March 18, 1996
2. Can action be taken at a later date?
No. If no, why not? Trial Project
Improvements need to be completed this summer
If
there is a memo addressing the following issues. you may attach and reference
the memo, but please highlight it so staff can easily answer I ‑ V
I. SUMMARY
OF ISSUE:
In July of 1994, the
City, applied for special Federal Highway Improvement funds for Traffic Calming
Improvements for Stevens Avenue. We requested $287,000 of Congestion Mitigation
and Air Quality (CMAQ) funds to complete temporary and permanent improvements
along this arterial as well as an education program (see attachment A).
In October of 1994,
Dana Connors, then Commissioner of the Maine Department of Transportation,
selected the City's project for traffic Calming Improvements" for Stevens
Avenue for funding. The City/state Agreement formalizes the details of the
grant acceptance by the City (see attachment B).
This project was
defined in detail for the Public Safety Committee on January 10th and at a City
Council Workshop on January 29th, 1996.
II. REASON
FOR SUBMISSION: (What issue /
problem will this address?)
The City/State
Agreement must be accepted and approved by the Portland City Council prior to
expenditure of funds.
III. INTENDED
RESULT: (How does it resolve the
issue/problem?)
Favorable City Council
action will permit the proposed project to proceed forward. The Memorandum of
Agreement will be signed by both parties, at that time, a contract will be
prepared for a qualified consulting engineering firm to complete the necessary
design work. Public Works, Traffic staff will be overseeing the project. 'The
temporary improvements are scheduled to be implemented before start of the 1996‑97
school year.
IV. FINANCIAL IMPACT:
As detailed in Section
II.A, in the Memorandum of Agreement, the City is obligated to pay 19.72% of
the cost of the project or a total of $56,596.40. Under terms of the Agreement,
the City is eligible for reimbursement of all expenses incurred on the project
excluding administration, supervision and overhead. The FY95 CIP has identified
$25,000 for this project. The FY96 CIP has identified the remaining $33,000.
V. STAFF ANALYSIS& RECOMMENDATION:
Public Works Traffic
Section personnel submit this Agreement for approval from the City Council. A
major effort has been put forth 'in preparation of the grant application, as
well as lobbying both MDOT and FHWA for approval of the project.
We feel that the
improvements and test program
will
teach us valuable information on traffic calming
standards and details as well as improve pedestrian safety. Therefore, we
recommend approval of the attached Memorandum of Agreement.
Attachment(s)
Prepared
by:
MaryAnn
Conroy, Principal Traffic Engineer Date
MEMORANDUM‑TRAFFIC DATE: March
6, 1996 TO: Bob Ganley, City Manager FROM: Nadeen Daniels,
Director of Public Works RE: Stevens Avenue Traffic Calming Project
CC: Councilor Harlow
Councilor Kane
Sonia Bean, Secretary ‑
City Manager
Elizabeth Boynton,
Corporation Council
William I Bray, Deputy
Director PW
Bruce Bell, Operations
Manager
Mary Ann Conroy,
Principal Traffic Engineer
Joe Gray, ‑Planning
Paula Craighead, resident The Traffic Section
requests that the attached Council Order be submitted at the March 18th Council
Meeting. Since 1992, the
Traffic Staff has been working with the Stevens Avenue area residents,
businesses and other City Staff to study pedestrian, bicycle and vehicular
movement on Stevens Avenue. The study was initiated at the request of the neighborhood residents who are concerned about safety issues along Stevens Avenue. The safety issue was exasperated on January 7, 1992, when a crossing guard in a crosswalk was struck by a vehicle which "failed to yield". This is an overstatement: the guard was almost hit, when a car that was rear-ended got pushed into the crosswalk by the car behind it. This incident generated Paula Craighead's letter to DPW head George Flaherty. Stevens Avenue passes
through a densely developed residential neighborhood which includes the
presence of 2,500 school children, residents, an elderly complex, churches and
a central business district. Specifically, the
neighborhood asked that we research and review the traffic control measures
that could (1) effectively slow down traffic, (2) improve pedestrian mobility,
and (3) improve overall safety along this area. The development of the mitigation strategies required continuous involvement of a Study Committee, a team of consultants and the community. This diverse group insured development of a product which would accomplish the identified goals and also be acceptable to the community. Except that the only people from the community were the 30 supporting the project. 526 people, including all businesses and residents actually on Stevens signed a petition against the project. Those petitions were "lost" by the city clerks office within a week of filing.
The Study Committee
consisted of (15) residents, (5) school officials, (6) business owners, and (9)
staff. Several public meetings, one on one meetings and Committee Meetings took
place periodically.
Over the four year
review process, we have jointly developed a plan of action to implement
"Traffic Calming" measures along Stevens Avenue. We have completed
our final report and preliminary designs.
In July 1994, the City
applied for Congestion Mitigation Air Quality (CMAQ) funds for Traffic Calming
Improvements for a total cost of $287,000. In October of 1994, MDOT approved
and funded 80% of the project.
The attached
City/State Agreement formalizes the details of the grant acceptance by the City.
The City is responsible for 20% of the total project cost or $57,400. The 95
CIP included $25,000 for this project and the 96 CIP included the remaining
$33,000.
The plan includes
three distinctive areas: (1) temporary improvements and monitoring, (2) permanent improvements, and (3) an Educational
program. The permanent improvements will be determined in detail after careful
review of the monitoring data.
The temporary improvements (the asphalt berms) were so
unpopular they lasted only 3 weeks before they were taken out. In actuality the“temporary" improvements were
never
meant to be removed. Calling them“improvements" also implies that they are
such, which the changes manifestly were not. The consequent
monitoring program and MDOT accident data showed an 8% drop in both pedestrians and bikers, in
addition to a 58% increase
in accidents, and a pollution increase of more than 450 tons a year. .
The results of this project significantly interest all municipalities in the State of Maine as well as MDOT. Some of these transportation concepts are very innovative for our region. Therefore, we have included a very extensive and detailed monitoring program to test the temporary improvements prior to any permanent construction on this project Results of said monitoring program, in addition to public opposition were ignored .
The Executive Summary
prepared by the team of Consultants was submitted and presented to the Public
Safety Committee on January 10th and the full City Council at their January
29th Workshop.
The Traffic Section recommends approval of the
proposed City Council Order.
CONGESTION
MITIGATION/AIR QUALITY
PROGRAM
APPLICATION
FOR
STEVENS
AVENUE
PORTLAND,
MAINE
SUBMITTED
BY
CITY
OF PORTLAND
CONGESTION MITIGATION AIR QUALITY PROGRAM APPLICATION Part 1 ‑ General
Information I.1 Applicant Name, Address and Phone
Number Applicant
Name: City of Portland Contact:Mary
T'heriault Address:65
Hanover Street Portland,
Me 04101 Phone:207‑874‑8894 I.2 MPO/Municipal Coordination: Attachment I ‑
is a letter from PACTS stating that the proposal is being considered by both
PACTS committees for compliance with the MPO's plan. A formal letter will
follow. 1.3pan
style='mso-tab-count:1'> Project Location ThThe project is located on
Stevens Avenue in Portland as described below. The general location is shown in Figure I of Attachment Permanent traffic
calming. measures: span>Stevens Avenue from Pleasant Street to
Woodford Street. This section is approximately 1,600 feet long anand
located in front of Deering High School and the Longfellow School. Permanent
measures are also requested on Stevens Avenue in front of the Lincoln School.
This section is 400 feet long, Temporary traffic
calming measures: span>A temporary I I pilot
program is also planned between these two sections. I.4 Project
Type Based upon the categories contained in the CMAQ Proposal Selection Policy, the project is applicable to the following categorie Type: Transportation Control Measures
(ix) programs for secure bicycle storage facilities and other
facilities, including bicycle lanes, for the (x) programs and ordinances to facilitate
non‑automobile travel, provision and utilization of mass transit, and to
generally reduce the need for single‑occupant vehicle travel, as part of
transportation planning and development efforts of a locality, including
programs and ordinances applicable to new shopping centers, special events, and
other centers of vehicle activity. Type
3: Bicycle and Pedestrian Facility Programs Construction of
bicycle and pedestrian facilities and traffic calming measures to enhance the
safety for pedestrians and bicyclists. I.5 Project Description The CMAQ funds will be used to implement traffic calming measures along portions of Stevens Avenue. Traffic calming incorporates physical alterations of the street along with signage to decrease speeds and increase the safety of both motorized and non‑motorized traffic. This project will be a
demonstration project of traffic calming measures on a minor arterial with an Annual Average Daily Traffic
Volume of 14,500 vehicles per day through a neighborhood with
numerous institutional uses including public schools (2,500 school children),
colleges, churches, and 14,500 cars a day does not equate to a minor
arterial. Just 3,000 cars a day makes it a major arterial, according to the
AASHTO Green Book, the Federal Highway Administration, and the Institute of
Transportation Engineers. Adding that it is a primary emergency vehicle access
route, and a transit route, --it's not a minor arterial in any way, and
the DPW knew it. The permanent and temporary traffic calming plan which the funds will be used to construct are included in the back of this application and include the following construction.
a. Construction of permanent traffic calming
measures on Stevens Avenue south of Pleasant Street to north of Woodford
Street. Traffic calming, measures planned for this section include:
Textured and/or
colored pavement in the parallel parking lane to visually narrow the street
width Bollards at neck downs to channelize pedestrian traffic A raised
crosswalk directly in front of the Longfellow school Ten foot wide flush
crosswalks with interlocking concrete pavers at various points along the
corridor Tree plantings (to be furnished by the City) Signage (to be
furnished by the City)
b. Construction of permanent traffic calming
measures in front of the Lincoln Middle
School consisting of
the following:
Extended raised area
of Stevens Avenue fronting the school. Neck downs with bollards Five ten foot
wide flush crosswalks with interlocking concrete pavers. Signage (to be
furnished by the City). Tree plantings (to be furnished by the City)
c. Temporary traffic calming measures on
Stevens Avenue between Pleasant Street and Lincoln School:
d. Topographic survey for the areas where the
permanent traffic calming measures are planned.
e. A monitoring program to determine the
effectiveness of both the permanent and temporary traffic calming measures.
This monitoring will include air quality testing. f. To design both the
permanent and temporary measures. g. A city wide educational and marketing project in
the adjacent schools to promote public awareness I.6 Estimated Project Costs 1.6.a Construction
Costs A complete construction cost estimate is included as Attachment 2 to this application. I.6.b Amount of CMAQ request In addition to the
construction costs in areas where the permanent plan will be implemented, CMAQ funds
are requested to design the permanent plan; to install and monitor a temporary devices plan which will be
reflective of the permanent traffic calming for the balance of the corridor,
and for an educational program. The temporary devices will be in place for a
period of 12 months during which time a traffic study replicating that of the
Phase I Traffic Study analysis will be performed to test the effectiveness of
the measures. The data collected from this monitoring program will be utilized not only to evaluate the
effectiveness of the proposed permanent plan on Stevens Avenue, but can be
transferred to other communities and arterials throughout the State. The “temporary devices” were a series of asphalt
berms (see photos) that were so poorly
operationally designed that they lasted just 3 weeks before public outcry
forced them off the road. The public did not like the design
configuration, as it was ugly, created mobility hazards, and decreased safety
for their children. The amount of CMAQ
funds requested are as follows:
Construction
Cost
$
214,000.00
Education
Program
10,000.00
Monitoring
‑ Evaluation of Pilot Program
15,000.00
Temporary
Improvements
30,000.00
Engineering
& Survey for Permanent Improvements 18,000.00
Total Requested $ 287,000.00
The total project
costs are $287,000.00 and the amount of CMAQ funds requested are 80% of this
amount, or $229,600.00.
I.6.c Amount of Non‑Federal Match
The City of Portland
will provide 20% of the project funds, $57,400.00, as the local match. In
addition to these monies, the City will provide the landscaping improvements.
1.7 Post CMAQ Funding
When the permanent
traffic calming improvements planned for Stevens Avenue are completed, the City
of Portland will maintain the street. The City agrees to maintain the
temporary measures for a 24 month period. If a subsequent grant is not approved,
then the City agrees to remove the
temporary measures*. A letter from the
commitment from the City is attached to this application as Attachment 3. (*Which sounds nice, but as DPW head William
Bray told a caller one day "The humps were never meant to be removed.” Removal was a lie to get funding. The
“subsequent grant”
was not approved
, as air pollution went up 46% (city) or 400-600% (FHWA).)
1.8 Proposed Construction/Implementation
Schedule
Should the project
receive CMAQ funding, the following implementation schedule will be followed:
Traffic
Calming Event
Beginning
Date Completion Date
Survey
and Design Improvement
10/1/95 4/l/96
Implement
Permanent &
Temporary
Measures
4/l/96 8/l/96
Monitor
Permanent &
Temporary
Measures
3/1/96 7/1/97
I.9 Matching Funds
The City of Portland will provide the non‑federal
CMAQ cost share of $57,400.00. A letter from the City is included as Attachment
3.
I.10 Who Would
Design and Construct/Implement This Project?
A qualified professional will be retained to design
the project through a qualification‑based contract selection procedure.
These professionals will be selected through a formal Request for Proposals and
interview procedure complying with local State and Federal guidelines. The
project construction will be publicly advertised for bid to contractors
including the City's new public works construction company and the lowest
qualified bidder will be awarded a contract to implement the project. The qualified professional also got told what the city wanted to hear, and supplied it .
Part
11 ‑ Specific Information
II.A.1
Initial Ozone Precursor Reductions Data used in analysis Traffic calming measures should reduce the average travel speed by up to 10 mph The AADT on Stevens Avenue is 14,500 vehicles per day
Traffic calming generally encourages more use of walking, bicycles and
calmer driving. Based on data published in Germany, a 10-mile reduction in
speed through traffic calming reduces idle time by 15%, gear changing by 12%,
brake use by 14% and gasoline use by 12%.
Based upon the above experience, and a study
entitled "Winning Back the Cities" by Peter Newman and Jeff Kenworthy, it is assumed there will be no change in VOC emission and a 32%
reduction in NOX.
This "Buxtehude, Germany study” and
“Winning” are the only environmental data offered as evidence of air
improvement anywhere in this application, and they are both wrong, according to
the EPA.
It is assumed that traffic
calming will reduce the local trips by 7.5%.
Estimated VOC reduction:
Estimated NOX reduction:
NOX emission at
35 mph = 2.14 grams/mile traveled.
Notice the speed
used to calculate the air quality improvement!
2.14 x 0.32 = 0.68
grams/vehicle reduction per traveled mile
Corridor length =
3,950/5,280 = 0.75 miles
0.68 grams
x 0.75mi
x 14,500 vehicles x 0.925 x I kg.
= 6.8 kg/day
veh. Mile day 1,000g
bv x 14.500 veh
x 1kg =1.75
kg/day
veh. mile
'Total 6.8 + .75 = 8.55 kg,/day
II.A‑2 Potential Long‑Term Air
Quality Benefits
Estimated VOC Reduction:
“None” is exactly
right- because VOC outputs went UP 46%!
Estimated NOX Reduction:
8.55 kg/day (see
calculations for initial)
This daily estimated
reduction in NOX will continue throughout the 20 year design life of the
project provided the temporary measures also are later implemented on a
permanent basis.
II.A.3
Benefit/Cost Ratio
Estimated VOC Benefit Cost
Ratio:
0 grams/day/$1
Estimated NOX Benefit Cost
Ratio:
= 8.55 kg/day x 1,000 gm/kg
= 8,550 gms/day
= 8,550/$229,600 = 0.037
gms/federal CMAQ dollar Again, all based upon
a speed of 35 MPH, which is not going to happen.
II.B
Qualitative Analysis The
general belief based on generalized vehicle emission tables is that traffic
calming will not benefit the air quality and may in fact increase vehicle
emissions. There is no experience in Maine and little in the United States that
documents the effect of traffic calming on air quality. Based on published
data, the City of Portland believes the proposed traffic calming measures will
improve the air quality.
This "general belief " exists because it has been known for over 25
years by traffic and environmental engineers that the slower traffic goes, the
more it pollutes. Seeing that traffic calming slows traffic, Portland
traffic engineers would know this. There is lots of experience nationwide on
how slower traffic generates more pollution. The published data
quoted (though not shown) is wrong, according to the EPA. This
demonstration project will offer the opportunity to document the air quality
changes associated with traffic calming. Many of the significant traffic
calming projects in Europe have been sponsored as demonstration projects by
both the local and federal governments to test the effect of calming on key
environmental
Research on traffic calming in Europe shows that in
built up areas the
higher the vehicle speed, the greater the frequency
of acceleration,
deceleration and braking, all of which add to air
pollution. Contrasting this
study is German evidence showing that in residential
areas idle times are
reduced by 15%, gear changing by 12%, brake use by
14%, and ‑gasoline by
12% due to the effects of slower, calmer and more
uniform driving. In
Buxtehude, Germany, which has a population of 33,000
people. A traffic
calming demonstration project documented changes in
different types of
emissions for two styles of driving when the speed
was reduced from 30 to
18 mph. Again, the erroneous Buxtehude study……. Driving Style Emission Type 2nd Gear
Aggressive 3rd Gear Calm CO ‑17% -13% HC ‑10% ‑22% NOX ‑32% ‑48% Fuel Consumption +7% ‑7% In addition to calming and more uniform driving, it
is anticipated that implementation of traffic calming measures may reduce the
number of trips within the neighborhood. For example, many of the parents who
currently drive their children to and from school and related activities, may
decided after traffic calming measures that the street is safe enough to allow
their children to bicycle
or walk to school. Except that the school doesn’t allow them to ride their bikes. —sounds nice though…… II.C
Additional Considerations II.C.1
Congestion Impacts It is anticipated that the proposed traffic calming project will reduce congestion by reducing the number of internal neighborhood trips by making the street safer for children to bicycle or walk to school and by diverting through truck traffic to roadways where there is less congestion. This is a lie: The only other roads with less traffic are the neighborhood streets, and supporters don't want trucks on them. Forest, Warren, Congress, and Brighton, the only other major roads anywhere near Stevens, all carry more traffic. Sounds good though, for funding. The peak hour traffic along one of the more
congested areas of Stevens Avenue, near Deering High School is 1,047 vehicles
per hour (vph). The City estimates that this project may result in a 7.5%
reduction in local trips (non‑through) and a 25% reduction in truck
traffic which will reduce the peak hour traffic in front of the high school
from 1,047 vph to 969 vph,
which is calculated as follows: PM peak hour two way traffic = 1,047 5% of traffic is trucks (1,047 x 0.05 = 52) 70% of traffic is non‑through traffic
[0.7 x (1,047 ‑ 52)=6971] Computed reduction in traffic: 0.075 x 697 = 52 ‑ Reduction in truck traffic: 52 x 0.5 = 26 Total traffic reduction: 52 + 26 = 78 Percent reduction in congestion: 100 x
(78/1,047) = 7.4%
II.C.2 VMT
Impacts The project is estimated to reduce the VMT/day as
follows: AADT = 14,500 0.074 x 14,500 vpd x 0.75 = 805 VMT/day reduction II.C.3 Education The project provides an excellent stage to promote a
City wide public awareness of the transportation mode choice/air quality
relationship. The marketing approach will include the community, bus access and
public officials in the program. The pedestrian and bicycle facilities are
intended to be highlighted in this project to promote their use. Highlighting
will be accomplished through textured paving, painting, bump outs at pedestrian
crossings, and signage. The location of the project
relative to five schools/colleges provides an excellent tool for both the
faculty and City to teach students about the benefits of reduced congestion,
transportation mode choice and air quality relationships. Never done. II.C.4 Other Long‑Term Project Benefits The purpose of the traffic calming project is to
make the Stevens Avenue environment safer and more attractive. This usually
results in a greater level of pedestrian and bicycle activity. In Berlin's
Federal demonstration project, non‑motorized traffic on a wide range of
streets increased by between 27% and 114%. Similar results are documented
throughout Europe and it
is hoped that these effects can be realized on Stevens Avenue. Thus the
results of a demonstration project on Stevens Avenue could be utilized to
evaluate future projects. II.C.5 Affect on Motorized Trips The project is expected to reduce motorized trips by
encouraging use of Stevens Avenue by bicycles and pedestrians. The percent
reduction is forecast to be 7.44 or 78 trips during the peak hour as discussed
in II.C., What it actually did is reduce pedestrians and
bikers by 8% each.
AGREEMENT
BETWEEN THE
STATE OF MAINE DEPARTMENT OF
TRANSPORTATION
AND THE
CITY OF PORTLAND
REGARDING
TRAFFIC CALMING ALONG
STEVENS AVENUE
FEDERAL AID PROJECT NO. CM‑6869(00)/PIN
6869.00
This AGREEMENT is entered
into on this day
of 1996 by
and between
the STATE OF MAINE DEPARTMENT OF
TRANSPORTATION (hereafter DEPARTMENT) and
the CITY OF PORTLAND, a body corporate and
politic located in the County of Cumberland
(hereafter CITY) regarding the development,
design, construction and/or implementation of traffic
calming measures along portions of Stevens
Avenue in Portland (hereafter project) as follows:
I.
PROJECT DEVELOPMENT
A. The
CITY shall submit an acceptable line item budget to the DEPARTMENT for approval
which contains an itemization of project costs as directed by the DEPARTMENT.
Once such a budget is approved, expenditures may exceed any single cost
category or budget line item amount by up to ten (10%) percent without
modification provided that the total of all such expenditures does not exceed
the total amount allowable for the project as hereinafter provided under
Paragraph N below.
B. The
CITY shall not perform or authorize any services or work under this Agreement
without first receiving the express approval to do so in writing from the
DEPARTMENT.
1. Such approval shall be contingent upon the DEPARTMENT
receiving authorization from the Federal Highway Administration (hereafter
FHWA) for federal participation in the project costs here before described
under Paragraph A above. The DEPARTMENT shall not unreasonably withhold such
approval.
2. All costs incurred by the CITY prior to receiving
such approval from the DEPARTMENT shall
be ineligible for federal participation and therefore not reimbursable by the
DEPARTMENT under the provisions of Article II.
3. The
CITY shall develop and prepare all of the necessary design plans,
specifications, estimates, bid documents and contracts for the project as
directed by the DEPARTMENT in accordance with the DEPARTMENT's current
standards and procedures for federal‑aid projects. The CITY shall submit
all such plans, specifications, estimates, documents and contracts to the
DEPARTMENT for review and approval. PIN 6869.00 All design features shall conform to AASHTO standards or
equivalent. Unless the
guidelines interfere with what the City Council wanted to do, in which case
they were ignored 2. All
plans shall adhere to the DEPARTMENT's utility accommodation policy as set
forth in its "Policy On Above Ground Utility Locations" as revised
November 1987. D.
The CITY may contract for engineering and design related services as necessary
to develop, design, construct or implement the project, provided nevertheless: 1. The
selection and retention of any individual or firm to provide or furnish any
engineering or design related services for the project (hereafter consultant)
shall be accomplished in accordance with the DEPARTMENT's current consultant
selection and retention procedures. 2.
No contract for such services shall be awarded without the
express approval of the DEPARTMENT and FHWA pursuant to the provisions set
forth under Part 172 of Title 23 in the United States Code of Federal
Regulations (hereafter CFR) specifically, those provisions set forth therein
under Section 172.5(d). a, The
CITY shall specifically monitor all work performed under any such contract
pursuant to the provisions of 23 CFR 172.13. b. The
DEPARTMENT may accept or reject any work performed or procured under any such
contract pursuant to the provisions 23 CFR 172.5(d). E. The
CITY shall develop and prepare all environmental studies ‑and reports
necessary for the project as directed by the DEPARTMENT. All such studies and
reports shall be submitted to the DEPARTMENT from time to time for review,
comment and acceptance. F. The DEPARTMENT shall prepare and submit to FHWA for concurrence all environmental documentation required for the project under the provisions of the National Environmental Policy Act (NEPA) G. The CITY shall obtain all permits necessary to construct the
project. H.
The CITY shall provide for adequate public participation as directed by the
DEPARTMENT during the development of the project. I. The
CITY, at its own expense, shall acquire or furnish any additional right of way
that might become necessary to construct or implement the project, provided
nevertheless: 1. All such right of way shall be acquired in accordance with
the Uniform Relocation Assistance and Real Property Acquisition Policies Act of
1970, as amended by the United States Congress in 1987, pursuant to the
provisions set forth under 49 CFR Part 24. PIN 6869‑00
2.
All
such right of way shall be acquired prior to advertising for bids and shall be
held inviolate from all encroachments. The CITY shall certify to the DEPARTMENT
that all such right of way has been acquired prior to being allowed to
advertise for bids as hereinafter provided under Paragraph J below.
3
No
reimbursement shall be allowable under the provisions of this Agreement for the
cost of acquiring any right of way.
J.
Upon
approval by the DEPARTMENT, the CITY shall advertise and award a contract to
construct or implement the project as directed by the DEPARTMENT.
I
Both
the CITY and the DEPARTMENT shall have the right to accept or reject any and
all bids received as a result of such advertisement.
2.
The
CITY shall not award any contract to construct or implement the project without
the express approval of the DEPARTMENT.
3
Any
contract to construct or implement the project shall prescribe that the project
shall be constructed or implemented in accordance with the plans and
specifications approved by the DEPARTMENT and in compliance with the
DEPARTMENT'S current Standard Specifications for Highways and Bridges
(hereafter Standard Specifications).
4.
Prior to the beginning of
any construction or implementation, the CITY shall arrange for a
preconstruction meeting to coordinate the construction or implementation of the
project with the DEPARTMENT, any and all contractors, utilities and any other
parties directly involved in the construction or implementation of the project.
5,
Traffic
throughout all work areas of the project shall be controlled in accordance with
the provisions of Part VI of the Manual on Uniform Traffic Control Devices for
Streets and Highways.
6. Any work involving force account procedures shall require
the express approval of the
K.
The
CITY shall provide all of the necessary supervision, inspection and
documentation to ensure that the project is completed satisfactorily and
constructed or implemented in accordance with the provisions and specifications
of any contract.
1
The
CITY shall provide a full‑time qualified employee to be in responsible
charge of the project.
2.
The
CITY shall use procedures acceptable to the DEPARTMENT to document the quantity
and quality of all work performed under this Agreement in an accurate and
uniform manner. All such documentation including all source documents used as
the basis of payment for such work shall become a matter of record and retained
as hereinafter provided under Article III, Paragraph A.
3. The
CITY shall provide all testing as directed by the DEPARTMENT. 4. Upon
completion of the project, the CITY shall provide a compliance certification
that the project was constructed or implemented, quantities measured and
documented, and materials tested in accordance with the specification
requirements of any contract as well as the policies and procedures approved by
the DEPARTMENT. L. The
DEPARTMENT may inspect the project and all documentation pertaining thereto at
any time during the period of construction or implementation and may test any
of the materials used therein to ensure compliance with the provisions and
specifications of any contract. The DEPARTMENT may reject any work or materials
not in such compliance. Upon completion of construction or implementation, the
DEPARTMENT may inspect the project to determine the acceptability thereof prior
to paying any final claim for reimbursement of project costs as hereinafter
provided under Article II, Paragraph C.2. M.
Upon completion of the project, the CITY shall provide the DEPARTMENT with a
set of reproducible as‑built plans of the project on mylar or equivalent
archival quality material acceptable to the DEPARTMENT suitable for permanent
filing. . N. The
CITY shall make no changes in the project, except as hereinafter provided,
without the express written approval of the DEPARTMENT. 1,
An approved change shall be required to increase the cost of the project
whenever expenditures are expected to exceed any approved single cost category
or budget line item amount by ten (10%) percent or whenever the total of all
participating project costs as hereinafter defined under Article 11, Paragraph
A is expected to exceed the sum of Two Hundred Eighty‑Seven Thousand
($287,000) Dollars. In no event shall the total of all such participating
project costs exceed the sum of Two Hundred Eighty‑Seven Thousand
($287,000) Dollars without the express written approval of the DEPARTMENT. Approved
changes shall also be required to revise, modify or change the scope or
objectives of the project or any of the cost sharing or reimbursement
provisions set forth herein, to extend or shorten the period of this Agreement
or to contract out or otherwise obtain the services of a third party to perform
any of the services incidental to the project, except as otherwise approved or
provided for herein.
The CITY
shall assure that all work undertaken pursuant to this Agreement conforms to
all applicable federal and State laws. Specific federal laws and
regulations covering such work are contained under Title 23 in the United
States Code (hereafter USC) for applicable statutory law and 23 CFR for
applicable administrative law. General administrative requirements relative to
federally funded activities are also contained under 49 CFR Part 18 entitled
"Uniform Administrative Requirements for Grants and Cooperative Agreements
to State and Local Governments ". Allowability for participating costs is contained in the Executive Office of
the President of the United States' Office of Management and Budget (hereafter OMB) Circular A‑87 entitled "Cost Principles for Stare and Local Governments".
P. The
CITY shall develop and implement a maintenance plan acceptable to the
DEPARTMENT which assures an appropriate level of maintenance necessary to
maintain any of the permanent improvements or measures constructed or
implemented under the project in order to preserve the use and function thereof
as intended by the project. II. COST SHARING & REIMBURSEMENT
PROCEDURES A A
portion of the cost to develop, design, construct and/or implement the
project (hereafter project costs) shall be provided by the DEPARTMENT using
federal funds administered by FHWA under the provisions of the Intermodal Surface
Transportation Efficiency Act (ISTEA) of 1991. Federal funds (hereafter federal
share) shall be provided at the rate of eighty and twenty‑eight
hundredths (80.28 %) percent of all project costs deemed eligible for federal
participation (hereafter participating project costs) in accordance with all
applicable federal laws and regulations as hereinbefore referenced under
Article I, Paragraph 0 above. B. The
CITY shall be responsible for all of the non‑federal or matching share of
all participating project costs. The CITY shall also be responsible for all
project costs deemed ineligible for federal participation, including those as
hereinbefore provided under Article I, Paragraph 3.2 above and as hereinafter
provided under Paragraph C.5 below, unless otherwise agreed to in writing as
hereinbefore provided under Article 1, Paragraph NXXXXXX above. C. The
DEPARTMENT shall reimburse the CITY for all of the federal share of all
participating,, project costs hereinbefore described under Paragraph A above as
follows: 1. The CITY shall bill the DEPARTMENT no less than
monthly for all claims for all allowable direct and actual project costs
incurred under the provisions of this Agreement. Costs are incurred whenever
work is performed, a goods
and services are received or a cash =0 disbursement is made. All claims for such costs shall be submitted on
the CITY's billhead or invoice and be itemized in at least the same detail as
itemized in the approved project budget. Each claim so submitted shall include
an accumulative total for all costs incurred by cost category or budget line
item. Each claim shall also include a certification from a qualified employee
in responsible charge of the project that all amounts so claimed for
reimbursement are correct, due and not claimed previously and that all work for
which such reimbursement is being claimed was performed in accordance with the terms of this Agreement or any specific contract applicable thereto
approved by the DEPARTMENT under the terms of this Agreement. 2. In the event that less than One Thousand ($1000) Dollars in
such reimbursable costs are incurred in any one month period or regularly
scheduled billing period of at least one month duration, the CITY shall defer
any such claim therefore until the next month or regularly scheduled billing
period in which at least One Thousand ($1000) Dollars in such reimbursable
costs have been incurred or until the last or final claim is submitted for
reimbursement. Payment of any such final claim may be subject to a final inspection
of the project by the DEPARTMENT to determine the acceptability thereof as
hereinbefore provided under Article 1, Paragraph L.
3, The DEPARTMENT shall deduct all of the CITY's share of such
costs as hereinbefore described under Paragraph B above prior to making any
such reimbursement. The CITY shall show such share on all bills so submitted.
4.
The DEPARTMENT shall
reimburse the CITY for all participating project costs after deducting the
CITY's share of such costs as hereinbefore provided under subparagraph 3 above
until fifty (50%) percent of all such costs have been reimbursed, following
which, five (5 %) percent of all subsequent reimbursements shall be withheld
and retained by the DEPARTMENT until all work undertaken by the CITY pursuant
to this Agreement is completed satisfactorily.
a. All of that portion of such reimbursement so retained shall be
withheld and retained by the DEPARTMENT to the extent and in the same manner
set forth under the provisions of 23 M.R.S.A.
Section 52‑A.
b. Upon satisfactory completion of all work undertaken by the CITY
pursuant to this Agreement, the DEPARTMENT may release a portion of such
reimbursement SO
retained. The
remaining balance of such reimbursement so retained shall be withheld and
retained until such time as all things required of the CITY under this
Agreement are received, completed or accomplished to the satisfaction of the
DEPARTMENT. The DEPARTMENT, at its option, may retain temporarily or permanently,
from time to time, any portion of such remaining balance which it deems
equitable.
5. In the event that the CITY withdraws from the project, suspends
or delays work on the project or takes some other action, including any acts of
commission or omission, without concurrence of the DEPARTMENT which results in
the loss of federal participation in any of the reimbursable costs as provided
herein, the CITY shall be ‑ responsible for all of the federal share of
such costs and, if necessary, shall refund to the DEPARTMENT all of the federal
share of any reimbursements received which subsequently become ineligible for
federal participation.
III. RECORD RETENTION, ACCESS REQUIREMENTS
& AUDIT
A.
The
CITY shall maintain all project records for a period of three (3) years from
the date of the last or final submission of claim for reimbursement for project
costs in accordance with the provisions of 49 CFR 18.42(b), except as otherwise
provided under subparagraph I below.
1. In the event that any litigation, claim,
negotiation, audit or other action involving such records has begun prior to
the expiration of such period, then all records shall be retained until all
action and resolution of all issues arising therefrom are complete if such
action or resolution extends beyond the three year period hereinbefore de
2. The CITY shall assure that in accordance with the
provisions of 49 CFR 18.42(c), the
DEPARTMENT and FHWA, and if necessary, the
Comptroller General of the United
States, or any of their authorized
representatives, shall have full access at any and all
reasonable times to all records of the project
for all purposes necessary to make audits,
examinations, excerpts or transcripts.
B. The CITY shall assure that all applicable audit requirements
are met in accordance with the provisions of OMB Circular A‑128.
IV. GENERAL PROVISIONS
A, INDEPENDENT CAPACITY. The CITY, its employees, agents,
representatives, consultants or contractors, shall in performance of the work
under this Agreement act, in an independent capacity from and not as officers,
employees or agents of the DEPARTMENT.
B. CONTRACT ADMINISTRATOR. Following execution of this
Agreement, the DEPARTMENT shall assign a Project Leader to act as the '
Contract Administrator on behalf of the DEPARTMENT during the development of
the project under this Agreement. As the DEPARTMENT's representative, the
Contract Administrator shall have authority to stop the work if necessary to
ensure proper execution thereof in accordance with terms of this Agreement. All
bills or invoices for payment, progress reports, claims, correspondence and
all project related submissions from the CITY shall
be sent directly to the Contract Administrator.
C. EQUAL EMPLOYMENT OPPORTUNITY
1. During the performance of any work undertaken pursuant to
this Agreement, the CITY shall not discriminate against any employee or
applicant for employment relating specifically to any work under this Agreement
because of race, color, religious creed, sex, national origin, ancestry, age or
physical handicap unless related to a bonafide occupational qualification: The
CITY shall take affirmative action to ensure that all such applicants are
employed and all such employees are treated during any period of employment
under this Agreement without regard to their race, color, religion, sex, age or
national origin. Such action shall include, but not be necessarily limited to:
employment, upgrading, demotions, transfers, recruitment or advertising for
recruitment, layoffs or terminations, rates of pay or other forms of
compensation and selection for all forms of training and apprenticeships. The
CITY shall prominently post in conspicuous places readily available to all
employees and applicants for such employment hereunder, notices setting forth
the provisions of this paragraph.
2. In all solicitations or advertising for employees placed by
or on behalf of the CITY relating specifically to any work undertaken pursuant
to this Agreement, the CITY shall state that all qualified applicants shall
receive consideration for employment without regard to race, color, religious
creed, sex, national origin, ancestry, age or physical handicap.
The CITY shall send to each labor union or
representative of any of its employees covered by a collective bargaining
agreement or any other contract or understanding under which any labor, work or
services are to be furnished towards the project under the terms of this Agreement,
a notice advising all such labor unions or representatives of the CITY's
commitment under this Article and shall prominently post copies of such notice
in conspicuous places readily available to all such employees and applicants
for employment.
4. The CITY shall cause all of the foregoing equal employment
opportunity provisions under these paragraphs to be included in any contracts
for services or work undertaken pursuant to this Agreement in such a manner
that such provisions shall be binding upon each consultant or contractor except
that the foregoing provisions shall not apply to any contracts for purchasing
or furnishing standard commercial supplies or raw materials. To the maximum
extent feasible, the CITY or any such consultant or contractor shall list all
suitable employment openings with the Maine Job Service under the Maine
Department of Labor's Bureau of Employment Security. This provision shall not
apply to employment openings which the CITY or any such consultant or
contractor proposes to fill within its own organization. The listing of such
openings with the
Maine Job
Service shall involve only
the normal obligation which pertain thereto.
D. LIABILITY. Any amount paid out by the DEPARTMENT arising out
of or from any errors, omissions or failures on the part of the CITY to meet
professional standards of construction engineering and inspection shall be
recovered from the CITY by reductions in any reimbursements due it under the
terms of this Agreement or by any other legal means. The DEPARTMENT shall
promptly notify the CITY if any potential claim arises under the provisions of
this Article. The CITY shall be afforded full opportunity for a defense against
any such claim. If it is subsequently determined that any such reduction in any
reimbursement due the CITY by the DEPARTMENT was either arbitrary, capricious
or fraudulent, then any amount so reduced shall be paid promptly.
E. FAMILIARITY WITH LAWS AND INDEMINIFICATION. The CITY is
assumed to be familiar with and at all times ‑shall observe and comply
with all federal and State laws as hereinbefore prescribed and all local laws,
ordinances and regulations which in any manner affect the services or work
undertaken by the CITY or any of its consultants or contractors pursuant to
this Agreement. . The CITY shall indemnify and hold harmless the DEPARTMENT and
its officers, agents and employees from any and all claims, suits, actions,
damages and costs of every kind or nature arising out of or from any negligent,
intentional, malicious or criminal act, error or omission occurring as the
result of any performance or nonperformance of the work undertaken by the CITY
pursuant to this Agreement. It is expressly agreed and understood by the
parties hereto that neither the DEPARTMENT nor the CITY hereby waive any
immunities or rights they may have under the Maine Tort Claims Act.
F. INSURANCE. The CITY shall require any and all consultants,
contractors or subcontractors performing any of the services or work undertaken
pursuant to this Agreement to be insured in accordance with the provisions set
forth under Section 103.08 of the DEPARTMENT's Standard Specifications.
G. OWNERSHIP. All plans, reports, notes, papers or other
tangible work produced by or on behalf of the CITY under the terms of this
Agreement shall be the property of the DEPARTMENT and shall be turned over to
the DEPARTMENT upon request following completion or termination of the project.
The CITY shall be allowed an interest therein commensurate with its share of
the project cost.
H. SUBLETTING, ASSIGNMENT OR TRANSFER. The CITY shall not
sublet, sell, transfer, assign or otherwise dispose of this Agreement or any
portion thereof or any right, title or interest therein without the express written
consent of the DEPARTMENT. No contract, agreement or transfer of this Agreement
shall in any case release or relieve the CITY from any liability under this
Agreement.
I. INTERPRETATION AND PERFORMANCE. This Agreement shall be governed by
the laws of the State of Maine as to its interpretation and performance.
J. ENTIRE AGREEMENT. This Agreement contains the entire agreement
between the parties hereto relative to all matters of the project and neither
party shall be bound by any statement, correspondence, agreement or
representation made previous hereto which is not expressly contained herein.
K.
TERMINATION
I The DEPARTMENT may postpone, suspend, abandon or otherwise
terminate this Agreement upon written notice to the CITY and in no event shall
any such action be deemed a breach of contract. In the event that the reason
for termination is other than for any failure by the CITY, the DEPARTMTEINT
shall give the CITY a written thirty (30) day notice of termination.
Postponement, suspension, abandonment or termination may be taken for
any reason by the DEPARTMENT or specifically as the result of any failure by
the CITY or any contractor thereunder to perform any of the services required
under this Agreement to the satisfaction of the DEPARTMENT. Upon receipt of
written notification from the DEPARTMENT that this Agreement is to be
postponed, suspended, abandoned or terminated for any of the foregoing reasons,
the CITY or any contractor thereunder shall immediately cease all work or
services subject to such termination, except any work required to protect
public health and safety, and shall assemble all material that has been
prepared, developed, furnished, purchased or obtained ~nder the terms of this
Agreement and transmit or rum over the control of the same to the DEPARTMENT
within thirty (30) days following the effective date of such termination. Such
material shall include all documents, plans, computations, drawings, notes,
records, and correspondence and all construction materials in place or
purchased for the project pursuant to this Agreement. Upon receipt of such
material, the DEPARTMENT shall reimburse or arrange a settlement with the CITY
in one of the following manners:
a. If the postponement, suspension, abandonment or termination is for
any reason other than that set forth under subparagraph b below, the CITY shall
be reimbursed for all work or services accomplished up until the date of such
termination. b. If the postponement, suspension, abandonment or
termination is the result of any failure by the CITY or any contractor
thereunder to correct any unsatisfactory performance after receiving fifteen
(15) days written notice from the DEPARTMENT setting forth the basis of such
dissatisfaction, the CITY's reimbursement shall be limited to payment for
acceptable work or services accomplished up until the date of such termination. 2. The CITY may accept the DEPARTMENT's evaluation of the
work performed as hereinbefore provided or submit to arbitration as hereinafter
provided under Paragraph L below. In any event, the DEPARTMENT shall not
consider any further reimbursement of any kind or nature pending the outcome of
any such arbitration. L.
ARBITRATION 1 Any and all claims, disputes or matters in question
arising out of or relating to this Agreement or any breach thereof, which
cannot be disposed of by mutual agreement of the parties hereto, may be
submitted to arbitration conducted and governed by the rules of the American
Arbitration Association applicable to the construction industry in effect at
the time of the execution of this Agreement. The provisions of this Article
shall be specifically enforceable under the prevailing arbitration law. 2, Should a demand for arbitration be submitted by either parry
to this Agreement, both parties shall have full right of discovery to all
books, documents or other tangible things to the extent permitted by the Maine
Rules of Civil Procedures. V. TERMS OF AGREEMENT A. All of the provisions set
forth under Articles I and II shall expire upon satisfactory completion of the
terms set forth therein or three (3) years from the date hereof, whichever
occurs first, unless otherwise terminated sooner or extended later by virtue of
any other provisions set forth elsewhere in this Agreement. ‑ B. All of the provisions set forth under Articles III and IV,
except Article IV, Paragraph E, shall expire upon satisfactory completion of
the terms set forth under Article III unless otherwise terminated sooner or
extended later by virtue of any other provisions set forth elsewhere in this
Agreement. C. The provision set forth under Article IV, Paragraph E
shall remain in full force and effect indefinitely or until terminated,
modified or amended in writing by the parties hereto or by any operation of
law.
VI. APPROVAL
This
Agreement has been approved and signed in duplicate by the parties below and
becomes effective on the day and date first above written.
STATE
OF MAINE
DEPARTMENT
OF
TRANSPORTATION
By:____________________________
_________________________________
Witness
Theodore
H. Karasopoulos
Chief
Engineer
CITY
OF PORTLAND
By:________________________________
__________________________________
Witness
Robert
B. Ganley
City
Manager
CONGESTION MITIGATION/AIR
QUALITY
PROGRAM APPLICATION
FOR
STEVENS AVENUE
BETWEEN WALTON STREET AND
FOREST AVENUE
PORTLAND, MAINE
SUBMITTED BY
CITY OF PORTLAND
APRIL,
1996
Proposal for FY 1998 and FY
1999 Congestion Mitigation and
Air Quality (CMAQ) FUNDS via PACTS Organization: City of Portland Contact: Mary Conroy Telephone:. (207) 874‑8894 Project
Location: The project is located on
Stevens Avenue in Portland from Forest Avenue to Walton
Street. Project Purpose: The CMAQ funds will be used to implement traffic calming measures along
Stevens Avenue. The traffic calming project incorporates Physical alterations
of the street with signage to decrease speeds and increase safety of both
motorized and non‑motorized traffic. Project
Description: This project will be a demonstration project of traffic calming
measures on a minor
arterial with an annual average daily traffic volume of 14,400 vehicles
per day through a neighborhood with numerous institutional uses including
public schools (2,500 school children), colleges, churches, and elderly
housing. The information learned from the project will be utilized for projects
in other communities throughout the State and northeast. LIE The traffic calming plan which the funds will be
used to construct are included in the back of this application and include the
following: a) Topographic survey for the areas where the
permanent traffic calming measures are planned. b) Design of the permanent measures. c) Construction of permanent traffic calming
measures on Stevens Avenue between Forest Avenue and Walton Street. Detailed Cost Estimate: A complete opinion of cost
is included as Attachment 4 to this application. The amount
of the CMAQ funds requested are as follows: Construction Cost $359,391.70 Engineering & Survey $ 28,551.92 Total
Requested $387,943.62 The total project costs are $387,943.62 and the amount of
CMAQ funds requested are 80% of this amount, or $310,354.90. Source of
Local Match: The
City of Portland will provide 20% of the project funds, Supporting Study: Stevens Avenue Pedestrian
Study ‑ Final Report, November, 1995 by DeLuca‑Hoffman Associates,
Inc. Please
respond to the questions on the attached sheet: A. Quantitative Analysis (See attached
emission factors.) ‑ See
Attachment I B. Qualitative Analysis ‑ See Attachment 2 C. Additional Scoring Considerations ‑ See Attachment 3 D. Opinion of Cost ‑ See Attachment 4 E. Plan View of Project ‑ See Attachment 5 Attachment I Quantitative Analysis A.1. Initial
Ozone Precursor Reductions Data used in analysis: Traffic calming measures
should reduce the average travel speed by up to 10 mph and reduce local trips
by 7.5%. The AADT on Stevens Avenue
between Walton Street and Forest Avenue is 14,400 vehicles per day. Traffic calming generally
encourages more use of walking, bicycles and calmer driving. Based on data
published in Germany, a 10 mile reduction in speed through traffic calming
reduces idle time by 15%, gear changing by 12%, brake use by 14% and gasoline
use by 12%. Based upon the above
experience, and a study entitled "Winning Back the Cities" by Peter
Newman and Jeff Kenworthy, it is assumed there will be no change in VOC
emission and a 32% reduction in NOX. Slowing traffic
creates almost no change in Nox, but does increase VOCs drastically. The city's
traffic engineers should have known this, based upon their stated years of
expertise in the field. It is assumed that traffic calming will reduce the
local trips by 7.5%. Estimated VOC reduction: None Estimated NOX reduction: NOX emission at 35 mph = 2.31 grams/mile traveled. 2.31 x 0.32 = 0.74
grams/vehicle reduction per traveled mile Corridor length from Forest
Ave. to Walton St. = 2,400/5,280 = 0.45 miles 0.74 –grams x
0.45mi x 14,400 vehicles x
0.925 x 1kq = 4.44 kg/day veh. Mile day 1,000g Additional
benefits of 7.5% reduction in local trips: 0.075 x [ 2.31 grams x
0.45] veh. Mile x 14,400 veh, x 1
kg day 1,000g
=1.12 kg/day Total 4.44 + 1.12 = 5.56 kg/day Potential Long‑Term
Air Quality Benefits Estimated
VOC Reduction: None see prior Estimated
NOX Reduction: 5.56 kg/day (see calculations for initial) This
daily estimated reduction in NOX will continue throughout the 20 year design
life of the project. Benefit/Cost Ratio Estimated
VOC Benefit Cost Ratio: 0 grams/day/$1 Estimated
NOX Benefit Cost Ratio: =
5.56 kg/day x 1,000 gm/kg = 5,560 gms/day =
5,560/$387,943 = 0.014 gms/federal CMAQ dollar Attachment 2 Qualitative Analysis B Qualitative
Analysis The general belief based on generalized
vehicle emission tables is that traffic calming will not benefit the air
quality and may in fact increase vehicle emissions. There is no experience in
Maine and little in the United States that documents the effect of traffic
calming on air quality. Based on published
data, the City of Portland believes the proposed traffic calming measures will
improve the air quality. This demonstration project will offer the opportunity
to document the air quality changes associated with traffic calming. Many of
the significant traffic calming projects in Europe have been sponsored as
demonstration projects by both the local and federal governments to test the
effect of calming on key environmental indicators. Research
on traffic calming in Europe shows that in built up areas the higher the
vehicle speed, the greater the frequency of acceleration, deceleration and
braking, all of which add to air pollution. Contrasting this study is German
evidence showing that in residential areas idle times are reduced by 15%, gear
changing by 12%, brake use by 14%, and gasoline by 12% due to the effects of
slower, calmer and more uniform driving. In Buxtehude, Germany, which has a
population of 33,000 people, a traffic calming demonstration project documented
changes in different types of emissions for two styles of driving when the
speed was reduced from 30 to 18 mph:
In
addition to calming and more uniform driving, it is anticipated that implementation
of traffic calming measures may reduce the number of trips within the
neighborhood. For example, many of the parents who currently drive their
children to and from school and related activities, may decided after traffic
calming measures that the street is safe enough to allow their children to
bicycle or walk to school. Again, the first sentence is a lie- this was written in 1994, 4
years after passage of the Clean Air Act. There were decades of air quality
experience available. Traffic engineers know that slower traffic means more
pollution. As traffic calming slows traffic, which was a stated goal of the
project, then more pollution is to be expected. To state that the results would
be unknown is lying. Again, the whole second paragraph is crap, as is the third: children
were not allowed to ride their bikes to school by school rule, a rule in place
for more than 25 years. Attachment 3 Additional
Scoring Considerations C.1 Congestion Impacts It is anticipated that the
proposed traffic calming project will reduce congestion by reducing the number
of internal neighborhood trips by making the street safer for children to
bicycle or walk to school and by diverting through truck traffic to roadways
where there is less congestion. This sounds good,
but is a lie. The project supporters did not want truck traffic on the local
side streets, nor the connectors between the arterials. As all the arterials in
the area other than Stevens were carrying much more traffic than Stevens, there
is therefore no place for truck traffic to go. The peak hour traffic on
Stevens Avenue between St. Joseph's College and Catherine McAuley High School
is 1,026 vehicles per hour (vph). The City estimates that this project may
result in a 7.5% reduction in local trips (nonthrough) and a 25% reduction in
truck traffic which will reduce the peak hour traffic in front of the high
school from 1,026 vph to 955 vph, which is calculated as follows: PM peak hour two way traffic
= 1,026 5% of traffic is trucks (1,026 x 0.05 = 51) 80% of traffic is non‑through traffic [0.8 x (1,026 ‑
51) = 780] Computed reduction in
traffic: 0.075 x 780 = 58 Reduction in truck traffic: 51 x 0.25 = 13 Total traffic reduction: 58 + 13 = 71 Percent reduction in congestion: 100 x (71/1,026) =
6.9% C.2 VMT Impacts The project is estimated to
reduce the VMT/day as follows: AADT = 14,400 0.069
x 14,400 vpd x 0.45 =
480 VMT/day reduction C.3 Education The project provides an
excellent stage to promote a City wide public awareness of the transportation
mode choice/air quality relationship. The marketing approach will include the
community, bus access and public officials in the program. The pedestrian and
bicycle facilities are intended to be highlighted in this project to promote
their use. Highlighting will be accomplished through textured paving, painting,
bump outs at pedestrian crossings, and signage The location of the project
relative to five schools/colleges provides an excellent tool for both the
faculty and City to teach students about the benefits of reduced congestion,
transportation mode choice and air quality relationships. C.4 Other Long‑Term Project Benefits The purpose of the traffic
calming project is to make the Stevens Avenue environment safer and more
attractive. This usually results in a greater level of pedestrian and bicycle
activity. In Berlin's Federal demonstration project, nonmotorized traffic on a
wide range of streets increased by between 27% and 114%. Similar results are
documented throughout Europe and it is hoped that these effects can be realized
on Stevens Avenue. Thus the results of a demonstration project on Stevens
Avenue could be utilized to evaluate future projects. It certainly is
not more attractive with the bright yellow signs and striping on the scarred-up
speed tables. Accidents
increased 58% after the table installation, so the road isn’t safer. Pedestrian and
bike usage dropped about 8% after they went in also. The results were
never publicized by the city, and were never considered in evaluation of any
other projects. C.5
Affect on Motorized Trips The project is expected to reduce motorized trips by
encouraging use of Stevens Avenue by bicycles and pedestrians. The percent
reduction is forecast to be 6.9% or 71 trips during the peak hour as discussed
in C.1. OPINION
OF COST Engineer's Opinion of Cost for Conceptual Improvements Steven's
Avenue ‑ Forest Avenue to Walton Street ‑ 2400 LF Portland,
Maine 1O‑Apr‑96 Description Unit Quantity Unit
Price Amount 202.11
Removing Portland Cement Conc Pavment SY 265 6.90 1828.50 202.202
Removing Pavement Surface SY 5550 2.50 13875.00 202.203
Butt Joint SY 450 4.50 2025.00 203.2
Common Excavation CY 310 7.30 2263.00 203.21
Rock Excavation CY 10 71.50 715.01 203.25
Granular Borrow CY 250 10.75 2687.50 301.09
Plant Mix Bit. Base Crse‑Grad B Ton 535 31.15 16665.25 304.1
Aggregate Subbase Crse‑Gravel CY 450 14.90 6705.01 403.07
Hot Bituminous Pavt ‑ Grading B Ton 550 35.50 19525.00 403.08
Hot Bituminous Pavt ‑ Grading C Ton 1200 30.60 36720.00 603.169
15" Culvert Pipe, Option III LF 1050 30.00 31500.00 604.072
Catch Basin, Type Al‑C EA 14 1445.00 20230.00 604.16
Altering Catch Basin to Manhole EA 6 570.00 3420.00 604.18
Altering Catch Basin or Manhole to Grade EA 23 335.00 7705.00 608.07
Reinforced Concrete Sidewalk SY 590 28.00 16520.00 608.15
Brick Sidewalk with Bitum. Base SY 200 94.00 18800.00 609.11
Vertical Curb Type 1 LF 580 24.85 14413. 00 609.12
Vertical Curb Type 1 ‑ Circular LF 250 30.10 7525.O0 609.34
Curb Type 5 LF 1005 18.50 18592.50 609.35
Curb Type 5 ‑ Circular LF 260 50.45 13117.00 609.38
Reset Curb Type 1 LF 190 13.10 2489.00 615.07
Loam CY 45 20.80 936.00 618.13
Seeding Method Number 1 Units 1 41.50 41.50 619.12
Mulch Units 1 15.10 15.10 621.285
Large Decicuous Tree (3" ‑ 3‑1/2" Cal)GPA EA 40 300.00 112000.00 627.407
Ref PI White or Yellow Pavt Marking SF 250 8.95 2237.50 645
Signage LS 1 1000.00 1000.00 652
Maint of Traffic LS 1 10000.00 10000.00 Engineering
(8.5% of total) LS 1 24101.82 24101.82 Survey LS 11 4450.00 4450.00 Subtotal (1999) $352,676.02 Contingency (10
%)
$35,267.60 Total (1999) $387,943.62 The Unit Prices in the estimate above were determined
utilizing cost data from MDOT project cost summaries accumulated from 8/31/94
to 8/31/95 in the area of urban construction and from similar projects recently
designed by this office. The total for the year 1999 is based on a 3% per year
increase in construction costs over four years. [the above cost opinion does not include amounts for the
following items, as cost impacts due to these items are not expected. ‑Relocation of utilities, ‑Acquisition of Right‑of‑Way, ‑Adverse soil conditions. CONGESTION MITIGATION/AIR
QUALITY PROGRAM APPLICATION FOR STEVENS AVENUE BETWEEN WOODFORD STREET AND CONGRESS STREET PORTLAND, MAINE SUBMITTED BY CITY OF PORTLAND APRIL, 1996 Proposal for FY 1998 and FY
1999 Congestion Mitigation and
Air Quality (dMAQ) FUNDS via PACTS Organization: Contact: Mary Conroy ‑ City
of Portland Telephone: (207)
874‑8894 Project Location: The project is located on
Stevens Avenue in Portland from Woodford Street to Congress
Street. Project
Purpose: The
CMAQ funds will be used to implement traffic calming measures along Stevens
Avenue. The traffic calming project incorporates physical alterations of the
street with signage to decrease speeds and increase safely of both motorized
and non‑motorized traffic. Project
Description: This project will be a demonstration project of traffic calming
measures on a minor arterial with an annual average daily traffic volume of
14,100 vehicles Per day through a neighborhood with numerous institutional uses
including public schools (2,500 school children), colleges, churches, and
elderly housing. The information learned from the project will be utilized for
projects in other communities throughout the State and northeast. The traffic calming plan which the funds will be
used to construct are included in the back of this application and include the
following: a) Topographic survey for the areas where the
permanent traffic calming measures are planned. b) Design of the permanent measures. c) Construction of permanent traffic calming
measures on Stevens Avenue between Woodford Street and Congress Street.
Detailed Cost Estimate: A complete opinion of cost
is included as Attachment 4 to this
application. The amount of the CMAQ funds requested are as follows: Construction Cost $402,180.10 Engineering
& Survey $ 28,454.43 Total Requested $430,634.53 The total project costs are $430,634.53 and
the amount of CMAQ funds requested are 80%
of this amount, or $344,507.62. Source of
Local Match: The
City of Portland will provide 20% of the project funds, Supporting
Study: Stevens
Avenue Pedestrian Study ‑ Final Report, November, 1995 by
DeLuca‑Hoffman Associates, Inc. Please
respond to the questions on the attached sheet: A. Quantitative Analysis (See attached emission
factors.) ‑ See Attachment 1 B. Qualitative Analysis ‑ See Attachment 2 C. Additional Scoring Considerations ‑ See Attachment 3 D. Opinion of Cost ‑ See Attachment 4 E. Plan View of Project ‑ See Attachment 5 Attachment 1 Quantitative
Analysis A.I. Initial
Ozone Precursor Reductions Data
used in analysis: Traffic calming measures should reduce the average
travel speed traveled along this section of Stevens Avenue by up to 5 mph and
reduce local trips by 7.5%. The AADT on Stevens Avenue between Woodford Street
and Congress Street is 14, 100 vehicles per day. Traffic calming generally encourages more use of
walking, bicycles and calmer driving. Based on data published in Germany, a 10
mile reduction in speed through traffic calming reduces idle time by 15%, gear
changing by 12%, brake use by 14% and gasoline use by 12%. Based upon the above experience, and a study
entitled "Winning Back the Cities" by Peter Newman and Jeff
Kenworthy, it is assumed there will be no change in VOC emission and a 16%
reduction in NOX. It is assumed that traffic calming will reduce the
local trips by 7.5%. Estimated VOC reduction: None Estimated
NOX reduction: NOX
emission at 35 mph = 2.31 grams/mile traveled. 2.31 x 0. 16 = 0.37 grams/vehicle reduction per
traveled mile Corridor length = 3,670/5,280 = 0.70 miles 0.37 grams x 0.70mi x 14,100 vehicles X 0.925 X 1kg = 3.38 kg/day veh. Mile day 1,000g Additional
benefits of 7.5% reduction in local trips: 0.075 x [ 2.31 grams x
0.70] veh. Mile x 14, 100 veh x 1 kq day
1,000g = 1.71 kg/day Total 3.38 + 1.71 = 5.09 kg/day Potential Long‑Term
Air Quality Benefits Estimated VOC Reduction: None Estimated
NOX Reduction: 5.09 kg/day (see calculations for initial) This
daily estimated reduction in NOX will continue throughout the 20 year design
life of the project provided the temporary measures also are later implemented
on a permanent basis. Benefit/Cost
Ratio Estimated
VOC Benefit Cost Ratio: 0 grams/day/$1 Estimated
NOX Benefit Cost Ratio: = 5.09 kg/day x 1,000 gm/kg
= 5,090 gms/day = 5,090/$430,634 = 0.012 gms/federal CMAQ dollar Attachment 2 Qualitative
Analysis Qualitative
Analysis The general belief based on generalized vehicle
emission tables is that traffic calming will not benefit the air quality and
may in fact increase vehicle emissions. There is no experience in Maine and
little in the United States that documents the effect of traffic calming on air
quality. Based on published data, the City of Portland believes the proposed
traffic calming measures will improve the air quality. This demonstration
project will offer the opportunity to document the air quality changes
associated with traffic calming. Many of the significant traffic calming
projects in Europe have been sponsored as demonstration projects by both the
local and federal governments to test the effect of calming on key
environmental indicators. Research on traffic calming in Europe shows that in
built up areas the higher the vehicle speed, the greater the frequency of
acceleration, deceleration and braking, all of which add to air pollution. Contrasting
this study is German evidence showing that in residential areas idle times are
reduced by 15%, gear changing by 12%, brake use by 14%, and gasoline by 12% due
to the effects of slower, calmer and more uniform driving. In Buxtehude,
Germany, which has a population of 33,000 people, a traffic calming
demonstration project documented changes in different types of emissions for
two styles of driving when the speed was reduced from 30 to 18 mph:
In addition to calming and more uniform driving, it
is anticipated that implementation of traffic calming measures may reduce the
number of trips within the neighborhood. For example, many of the parents who
currently drive their children to and from school and related activities, may
decided after traffic calming measures that the street is safe enough to allow
their children to bicycle or walk to school. Attachment 3 Additional
Scoring Considerations C.1 Congestion Impacts It is anticipated that the
proposed traffic calming project will reduce congestion by reducing the number
of internal neighborhood trips by making the street safer for children to
bicycle or walk to school and by diverting through truck traffic to roadways
where there is less congestion. The peak hour traffic along
this section of Stevens Avenue is 988
vehicles per hour (vph). The City estimates that this project may result in a
7.5% reduction in local trips (non‑through) and a 25% reduction in truck
traffic which will reduce the peak hour traffic in front of the high school
from 988 vph to 927 vph, which is calculated as follows: PM peak hour two way traffic
= 988 5%
of traffic is trucks (988 x 0.05 = 49) 70% of traffic
is non‑through traffic [0.7 x (988 ‑ 49) = 657] Computed reduction in
traffic: 0.075 x 657 = 49 Reduction
in truck traffic: 49 x 0.25 = 12 Total
traffic reduction: 49 + 12 = 61 Percent reduction in
congestion: 100 x (61/988) = 6.2% C.2 VMT Impacts The project is estimated to
reduce the VMT/day as follows: AADT = 14, 100 0.062 x 14,100 vpd x 0.70 = 730 VMT/day reduction C.3 Education The project provides an
excellent stage to promote a City wide public awareness of the
transportation mode choice/air quality relationship. The marketing approach
will include the community, bus access and public officials in the program. The
pedestrian and bicycle facilities are intended to be highlighted in this
project to promote their use. Highlighting will be accomplished through
textured paving, painting, bump outs at pedestrian crossings, and signagee The
location of the project relative to five schools/colleges
provides an excellent tool for both the faculty and City to teach students
about the benefits of reduced congestion,
transportation mode choice and air quality relationships. C.5 Other Long‑Term Project Benefits The purpose of the traffic
calming project is to make the Stevens Avenue environment safer and more
attractive. This usually results in a greater level of pedestrian and bicycle
activity. In Berlin's Federal demonstration project, nonmotorized traffic on a
wide range of streets increased by between 27% and 114%. Similar results are
documented throughout Europe and it is hoped that these effects can be realized
on Stevens Avenue. Thus the results of a demonstration project on Stevens
Avenue could be utilized to evaluate future projects. C.6 Affect on Motorized Trips The project is expected to
reduce motorized trips by encouraging use of Stevens Avenue by bicycles and
pedestrians. The percent reduction is forecast to be 6.2% or 61 trips during
the peak hour as discussed in C.1. OPINION
OF COST Engineer's Opinion of Cost for Conceptual Improvements Steven's
Avenue‑Woodfords St to Congress St ‑ 3670 LF Portland, Maine 1O‑Apr‑96
Subtotal (1999) $391,485.94 Contingency (10 %) $39,148 Total (1999)
$430,634.52 The
Unit Prices in the estimate above were determined utilizing cost data from MDOT
project cost summaries accumulated from 8/31/94 to 8/31/95 in the area of urban
construction and from similar projects recently designed by this office. The
total for the year 1999 is based on a 3% per year increase in construction
costs over four vears. The
above cost opinion does not include amounts for the following items, as cost
impacts due to these items are not expected. ‑Relocation of utilities, ‑Acquisition of Right‑of‑Way, ‑Adverse soil conditions. [1] (This is an overstatement: the guard was almost hit,
when a car that was rear-ended got pushed into the crosswalk by the car behind
it. This incident generated Paula Craighead’s letter to DPW head George
Flaherty.—ed.)
|